4-6. CHECKING UNPACKED EQUIPMENT.
a. General. The water system is packaged and shipped in 12 tricons and eight 50K water tank storage chests. Two
20K collapsible fabric tanks are stored in each chest. All other components of the water system are shipped in
tricon containers. Where possible, save crating inside the tricon for reuse. It will make repacking easier. When
uncrating the equipment, keep in mind that the system is made up of different connection kits. This manual
addresses installation and use of all connection kits, but you may not need all of these components to perform
your mission. Your operating requirements will determine which connection kits/components are needed to
perform the mission.
b.
Unpacking 50K Water Tank Chests. Refer to figure 4-1.
NOTE
Unpacking of one 50k water tank chest is shown. Unpacking of remaining chests is similar.
(1) Unfasten eight latches (1).
WARNING
The top cover is heavy and difficult to handle. Two personnel are required to lift top cover from
water tank chest.
(2)
Lift top cover (2) from water tank chest.
(3)
Move four handles (3) to OPEN position and remove end panel (4) from water tank chest. Repeat for
other end panel.
WARNING
The side panels are heavy and difficult to handle. Two personnel are required to lift side panels
from skid.
(4)
Unlatch four locking pins (5) and lift side panel (6) from skid (7).
(5)
Remove accessory components from water tank chest.
(6)
Lift divider pan (8) from skid (7).
(7)
Unfasten two tie down straps (9 and 10).
4-3