TM 10-4130-237-14
4-40.
STORAGE AND SHIPMENT INSTRUCTIONS (CONT)
18 Insert shipping plugs in water openings and secure in place.
19 If water chiller is mounted on trailer, disconnect two load binders.
20 Pull out four retaining pins. Pull out four carrying handles.
To prevent personal injury, four persons required to lift water chiller.
21 If mounted on trailer, slide water chiller out of trailer mounting kit.
22 Place water chiller in shipping container.
23 Place support kit components in shipping container.
4-41.
ADMINISTRATIVE STORAGE
a .
Storage Length and Readiness. Placement of equipment in administrative storage should be for short periods of
time (1 to 45 days) when a shortage of maintenance efforts exists. Items should be in mission readiness within 24 hours or
within the time factors as determined by the directing authority. During the storage period, appropriate maintenance re-
cords will be kept.
b.
Prior to Placing Unit in Storage. Before placing equipment in administrative storage, perform the next monthly/
quarterly preventive maintenance checks and services. All shortcomings and deficiencies should be corrected, and all
Modification Work Orders (MWOs) should be applied.
c .
Storage Site Selection.
Inside storage is preferred for items selected for administrative storage. If inside storage is
not available, the sites selected should provide required protection from the elements and allow access for visual inspection
when applicable.
4-112