Table 1. Operator Preventative Maintenance Checks and Services for the 3,000
and 5,000 Gallon Semi-Trailer Mounted Collapsible Water Tanks (continued).
ITEM
NO.
INTERVAL
MAN-
HOUR
ITEM TO BE CHECKED
OR SERVICED
PROCEDURE
EQUIPMENT
NOT READY/
AVAILABLE IF:
7
During
Filler/Discharge
Assembly
Inspect for proper
connection, evidence of
damage or leakage.
Connection is
damaged,
leaking or loose.
8
After
Bed Cloth (Models
91093 & 91094 only)
Inspect for damage.
Bed cloth is
damaged.
9
After
Water Tank/Envelope
Inspect for cuts, punctures
and leaks. Bolts loose or
missing where fittings
connect to tank.
Tank envelope
is cut, punctured
or leaks. Fitting
bolts loose or
missing.
10
After
Filler/Discharge
Assembly
Inspect for proper
connection, evidence of
damage or leakage.
Connection is
damaged,
leaking or loose.
END OF WORK PACKAGE