(20) Connect solenoid valve wires (2) to spade lugs (3) on harness wires. Slide looms (1) to cover wire
connections.
CAUTION
Do not start pump unless distributor pump is primed. Refer to para. 2-16 to prime pump.
(21)
Refer to para. 4-22 and connect battery cables.
(22)
Refer to para. 2-20 and fill water tank.
(23)
Refer to para. 2-6 and couple semitrailer to prime mover. Operate prime mover and pressurize air
system.
(24)
Refer to para. 4-63 and install spray nozzles.
(25)
Refer to para. 4-64 and install angle discharge valve.
(26)
Refer to para. 2-16 through 2-23. Operate spray system and check water piping and air lines for
leaks.
4-61. SUCTION AND FILL BUTTERFLY VALVES
THIS TASK COVERS:
a. Removal
c.
Assembly
b. Disassembly
d.
Installation
INITIAL SETUP:
Equipment Materials Required:
Tools Required:
Pipe Sealant (Item 11, Appendix E)
Nomenclature:
Personnel Required: 2
General Mechanics
Equipment Conditions:
Tool Kit
Ref
Conditions
1-10. b.(2)
Air reservoirs drained
2-14
Engine shut off
2-21
Water tank drained
a.
Removal.
(1) Remove eight nuts (1), washers (2) and screws (3) holding suction tee (4), suction butterfly valve (5) and
suction line (6) together. Remove suction valve (5).