2.13 PREPARATION FOR MOVEMENT.
To prevent contamination of water system components, keep dirt
mud, sand, and debris from entering open couplings during disas-
sembly.
a.
Disassemble Hose and Nozzle Kit.
(1) Disconnect all distribution nozzles, discharge hoses, reducers, and regulator from bag filler con-
nection kit.
(2) Drain water from all components and allow to dry. Install protective caps and plugs.
(3) Fold nozzle stands.
b. Disassemble Bag Filler Connection Kit.
(1) Disconnect all discharge hoses, gate valves, tees, Wyes and reducers from hose nozzle connec-
tion kit.
(2) Drain water from all components and allow to dry. Install protective caps and plugs.
c.
Disassemble Hose Nozzle Connection Kit.
(1) Disconnect all discharge hoses, gate valves, tees, distribution nozzles and reducers from 350
GPM pump connection kit.
(2) Drain water from all components and allow to dry. Install protective caps and plugs.
(3) Fold nozzle stands,
d. Disassemble Hose Connection Kit.
(1) Disconnect all discharge hoses, gate valves, tees, and reducers from 350 GPM pump connection
kit.
(2) Drain water from all components and allow to dry. Install protective caps and plugs.
(3) Fold nozzle stands.
e.
Disassemble 125 GPM Pump Connection Kit.
(1) Disconnect all discharge hoses, gate valves, check valve, reducers and 125 GPM pump from
350 GPM pump connection kit.
(2) Drain water from all components and allow to dry. Install protective caps and plugs.
(3) Prepare 125 GPM pump for movement in accordance with TM 5-4320-304-14 or TM
10-4320-309-14.
f. Disassemble 350 GPM Pump Connection.
(1) Disconnect all suction hoses, discharge hoses, tees, gate valve sand hypochlorination unit from
dual tank connection kit.
(2) Drain water from all components and allow to dry. Install protective caps and plugs,
(3) Prepare hypochlorination trait for shipment in accordance with TM 5-4610-233-13&P.
(4) Prepare 350 GPM pump for movement in accordance with TM 5-4320-226-14.