TM10-5430-229-13&P
(7) Install three new lock nuts (3), six flat washers (2), and three cap screws (1).
Section VI. PREPARATION FOR STORAGE OR SHIPMENT
4-16.
PREPARATION FOR STORAGE.
a. Intermediate Storage (46 to 180 days).
(1) Drain all water from the WTSC and all of its components.
(3) Mark the WTSC for intermediate storage in accordance with the standard Army procedures contained in TM
740-90-1, Administrative Storage of Equipment.
b. Long Term or Flyable Storage (Indefinite time) . Long term storage procedures are the same as for interme-
diate storage except the WTSC shall be marked for long term storage in accordance with TM 740-90-1, Administrative
Storage of Equipment.
4-17.
ADMINISTRATIVE STORAGE. Placement of equipment in administrative storage should be for short periods of
time when a shortage of maintenance effort exists. Items should be in mission readiness within 24 hours or within the
time factors determined by the directing authority. During the storage period appropriate maintenance records will be
kept.
Before placing equipment in administrative storage, perform all PMCS procedures. All shortcomings and deficiencies
should be corrected, and all Modification Work Orders (MWO) should be applied.
Storage site selection. Inside storage is preferred for items selected for administrative storage If inside storage is not
available, trucks, vans, conex containers and other containers may be used.
4-19/(4-20 Blank)