TM 5-3895-370-14&P
CAUTION
Preformed packings can fall out
easily. Use caution in assembling
valve bodes. Failure to comply might
result in damage to equipment.
(4)
Assemble inlet section (6), four valve bodies (7),
and outlet section (8).
(5)
Install tie rod (3), two lockwashers (5), and two
nuts (4).
(6)
Install two feet brackets (2), two tie rods (3), and
four nuts (1). Tighten nuts (4 and 1) to 20 lb-ft
(27 Nm).
NOTE
Follow-on maintenance: Install valve bank (para 4-134).
END OF TASK