l.
Disassemble Dual Tank Connection Kit Assembly. Each connection kit has been a assigned a kit number.
Components in kits 5 through 8 are positioned differently (opposite) kits 1 through 4 to allow interconnection of
all kits at the 350 gpm pump connection kit tees. Refer to figure 2- 36, sheet 1, to disassemble kits 1 though 4.
Refer to sheet 2 to disassemble kits 5 through 8.
WARNING
To prevent contamination of water system components, keep dirt mud, sand, and debris
from entering open couplings during disassembly. Make sure protective caps and plugs
are installed after components are disassembled.
Disassemble Kit No. 1, 2, 3, and 4. Refer from figure 2 -36, sheet 1.
(1)
Disconnect 20 foot discharge hose (17) and 10 foot discharge hose (18) from tee and gate valve
assembly (16).
(2)
Disconnect tee and gate valve assembly (16) from discharge hose (14).
(3)
Disconnect 20 foot discharge hose (14) from female discharge elbow (15) on water tank (19).
(4)
Disconnect 20 foot discharge hose (12) and 10 foot discharge hose (13) from tee and gate valve
assembly (11).
(5)
Disconnect tee and gate valve assembly (11) from discharge hose (9).
(6)
Disconnect 20 foot discharge hose (9) from female discharge elbow (10) on water tank (20).
(7)
Disconnect 10 foot suction hose (8) from tee and gate valve assembly (5).
(8)
Disconnect 20 foot suction hose (7) between tee and gate valve assemblies (5and 6).
(9)
Disconnect tee and gate valve assembly (6) from suction hose (3).
(10)
Disconnect tee and gate valve assembly (5) from suction hose (1).
(11)
Disconnect 20 foot suction hose (3) from male discharge elbow (4) on water tank (20).
(12)
Disconnect 20 foot suction hose (1) from male discharge elbow (2) on water tank (19).
Disassemble Kit No 5, 6, 7, and 8 Refer to figure 2-36, sheet 2.
(13)
Repeat steps (1) through (12) for kits 5, 6, 7, and 8.
(14)
Drain and allow components to dry.
(15)
Install caps and plugs on component couplings (para 2-10c).
(16)
Roll up all discharge hoses and secure with tape.
(17)
Prepare all 50K collapsible fabric tanks for movement. Refer to the applicable TM.