TM 10-4610-243-13
2-10. ASSEMBLY AND PREPARATION FOR USE - cont.
j.
Assemble 350 Gpm Pump Connection Kit (Distribution Point). Refer to figure 2-17.
WARNING
To prevent contamination of drinking water, make sure protective caps and plugs are
installed when components are not in use. Do not remove caps and plugs from
components until couplings are ready to be connected.
NOTES
Install all gate valves with hand wheel in upright position and valve fully closed.
Suction hoses are noncollapsible and discharge hoses are collapsible.
All components in this kit are 4-inch diameter.
(1)
Connect tee (1) to 10 foot discharge hose (2) (part of connection kit 4).
(2)
Connect 10 foot discharge hose (3) (part of dual tank connection kit no.5) to tee (1).
(3)
Connect 20 foot suction hose (4) to tee (1).
(4)
Connect tee (5) to 20 foot suction hose (4).
(5)
Connect 4-inch gate valve (6) to tee (5).
(6)
Connect 20 foot suction hose (7) to 4-inch gate valve (6).
(7)
Assemble, prepare for use and position 350 gpm pump (8) in water system. Refer to the
applicable TM.
(8)
Connect 20 foot suction hose (7) to female (suction) coupling on 350 gpm pump (8).
(9)
Connect of 20 foot discharge hose (9) to male (discharge) coupling on 350 gpm pump (8).
(10)
Connect 4-inch gate valve (10) to 20 foot discharge hose (9).
(11)
Connect 20 foot discharge hose (11) to 4-inch gate valve (10).
(12)
Connect tee (12) to 20 foot discharge hose (11).
(13)
Connect 20 foot discharge hose (13) to tee (12).
(14)
Assemble, prepare for use, and position hypochlorination unit (14) in water system. Refer to the
applicable TM.
(15)
Connect end of 20 foot discharge hose (13) to female (inlet) coupling on hypochlorination unit (14).
(16)
Connect 20 foot discharge hose (15) to male (outlet) coupling on hypochlorination unit (14).
2-48