TM 10-4610-243-13
2-10. ASSEMBLY AND PREPARATION FOR USE - cont.
q.
Prepare 50K Collapsible Water Tanks. Prepare water tanks for use in accordance with the applicable TM.
r.
Prepare 350 Gpm Pumps. Prepare 350 gpm pumps for use in accordance with the applicable TM.
s.
Prepare 125 Gpm Pumps. Prepare 125 gpm pumps for use in accordance with the applicable TM.
t.
Hypochlorination Unit. Prepare hypochlorination unit for use in accordance with the applicable TM.
2-11. INITIAL ADJUSTMENT
a.
Hoses. Couplings and Valves.
(1) Verify that all quick disconnect couplings are securely connected and locked.
(2) Verify that caps and plugs are installed on all open tees, fittings and hoses.
(3) Inspect suction and discharge hoses for kinks. Straighten out kinks and tight bends.
(4) Verify that all gate valves, quick acting valves and butterfly valves are closed.
b.
50K Collapsible Fabric Tanks. Perform initial adjustments in accordance with the applicable TM.
c.
350 Gpm Pumps. Perform initial adjustments in accordance with the applicable TM.
d.
125 Gpm Pumps. Perform initial adjustments in accordance with the applicable TM.
e.
Hypochlorination Unit. Perform initial adjustments in accordance with the applicable TM.
2-12. OPERATING PROCEDURES
a.
General. The 800K Water Storage and Distribution System has two primary modes of operation, fill and
discharge. In the fill mode, water is drawn from the water source and stored in the water tanks. During
discharge, water is removed from the water tanks and pumped to the distribution points. The water system
can operate in both fill mode and discharge mode at the same time.
b.
Water System Diagram. Refer to figure 2-24. Water flow to and from the collapsible fabric tanks is
controlled by gate valves identified by the prefix T. The number following the prefix tells which tank it
controls. The suffix "A" indicates that the gate valve controls water flow to the tank. The suffix B
indicates the gate valve controls water flow from the tank. By opening or closing the respective A (inlet)
or B (outlet) gate valves, the tanks may be filled or discharged.
c.
Startup. Refer to figure 2-24.
Change 1