TM 10-4320-303-13
Figure 2-35. Connection to Lead Pumping Station.
CAUTION
DO NOT leave hose on roadway or track that will be used by other vehicles.
Hoseline is easily damaged by rough handling or abrasive contact with rocks.
NOTE
Restrain hose assembly manually until first 50 feet of hose assembly is
in position.
After 50 feet of hose assembly is in position, the weight of the hose will
hold line in place.
h. Refer to paragraphs 2.3.8.2.4 through 2.3.8.2.7 and deploy hose assembly.
i. Continue to lay hose until hoseline in all four boxes has been flaked.
CAUTION
Swivel joints (Figure 2-36, 1) must be installed at every 1,000 feet in hoseline
(2). If not installed, hoseline (2) will twist during startup and cause damage to
equipment.
j. Repeat steps a through i (leaving out step g) to connect each truckload of hoseline to sections already
laid. Be sure to install swivel joints (Figure 2-36, 1) at every 1,000 feet in hoseline (2).
k. Connect hoseline (2) to each boost pumping station and storage assembly as those installation sites
are reached.
2-69