n. Remove grooved-end quick disconnect coupling clamp (10) (para 2.3.3.1) connecting check valve (9)
to discharge port (11) on 600 GPM pumping assembly, refer to applicable technical manual for
location of discharge port on 600 GPM pumping assemblies not shown. Remove check valve (9).
2.8.4 Preparation for Movement of Boost Pumping Stations. This is a general procedure for moving boost
pumping stations. For information pertaining to moving the 600 GPM pumping assemblies, reference
applicable technical manuals.
2.8.4.1 Disassembly Requirements. Disassembly of each boost pumping station requires the tools and
personnel referenced in paragraph 2.3.5.1. Pack the components listed in table 2-10 in the "PUMPING
STATION" crate after removing them from the boost pumping station.
2.8.4.2 Disassembly Procedures.
Figure 2-17. Disassembly of Boost Pumping Station (Suction Port).
NOTE
Set aside all removed components for repacking.
a. Remove 6 inch grooved pipe coupling (Figure 2-70, 1) (para 2.3.2.1) connecting lateral grooved pipe
fitting (2) to hoseline segment (3). Remove upline hoseline segment (3).
b. Remove grooved-end quick disconnect coupling clamp (4) (para 2.3.3.1) connecting lateral grooved
pipe fitting (2) to 6 inch butterfly valve (5).
c. Remove grooved-end quick disconnect coupling clamp (6) (para 2.3.3.1) connecting 6 inch butterfly
valve assembly (5) to discharge hose assembly (7). Remove 6 inch butterfly valve assembly (5).
d. Remove 6 inch grooved pipe coupling (8) (para 2.3.2.1) connecting hose assembly (7) to suction port
(9) on pumping assembly, refer to applicable technical manual for location of suction ports on 600
GPM pumping assemblies not shown. Remove hose assembly (7).
e. Install 6 inch grooved pipe coupling (8) (para 2.3.2.2) on end of hose assembly (7).
2-105